What is a progress claim in construction, and how do you get one paid?
A progress claim is a formal request for payment for work you have completed to date on a building contract. It is not a normal invoice: it must follow the contract and, in most states, the security of payment legislation, and the way you set it out decides how quickly you get paid and how hard it is for the other side to knock it back. Get it right and cash arrives on time. Get it wrong and a profitable job can still leave you short.
What is a progress claim?
On most building contracts you don't get paid at the end. You claim in stages, either at set milestones (slab, frame, lock-up, fixing, completion) or on a regular cycle, usually monthly. Each claim says: here is the work done to date, here is what has already been paid, here is what I am now asking for.
Builders often call it a "payment claim" or just "the claim". Under security of payment laws, a document has to meet specific requirements to count as a payment claim at all, and those requirements differ by state. Check yours with your lawyer or industry body.
How is a progress claim different from an invoice?
An invoice records a sale for tax purposes. A progress claim triggers a contractual payment process with its own deadlines, and in many cases a legal right to payment if it is valid. Many builders send one document that does both jobs, which is fine as long as it meets both sets of rules.
The practical difference is timing. A late or defective invoice is a nuisance. A late or defective progress claim can miss a reference date and push your payment back a full month.
What should a progress claim include?
Requirements vary by contract and state, but a solid claim usually has:
• The contract or job name and number, and who it is addressed to.
• The reference date or claim period it relates to.
• The work claimed, by stage or line item, as a cumulative total.
• Approved variations, listed separately, with their approval references.
• Less: amounts previously claimed or paid.
• The amount now claimed, plus GST.
• Any statement your contract or the legislation says must appear on the claim.
• Supporting evidence the contract requires (site reports, stage certificates, photos, subcontractor statements).
Claim cumulatively, not incrementally. A running total makes it obvious what has been paid and what is outstanding, and it is much harder to dispute.
What are the most common progress claim mistakes?
1. Missing the claim date. If the contract allows one claim per month and you miss the date, the cash moves to next month. Put reference dates in the diary at contract signing.
2. Claiming for work not done. Over-claiming might feel like helpful cash flow, but it distorts your WIP position and invites a dispute. Claim what you have earned. Our post on WIP reporting covers how to check.
3. Leaving variations out, or claiming unapproved ones. Approved variations belong on the claim. Unapproved ones belong on a register with an owner and a chase date.
4. Getting retentions wrong. Retention is held back from the amount due. Claim it, track it, and diarise the release dates, because nobody releases it automatically.
5. Sending it to the wrong person, in the wrong way. Service rules in the contract matter. A claim emailed to the wrong address may not count as served.
How do progress claims affect cash flow?
You pay wages, subbies and suppliers before the claim is made, then wait for the claim cycle, then wait again for the payment terms. On a typical job that gap runs six to eight weeks, and it grows when you win more work. That is why a profitable builder can run out of cash. The levers for shrinking it are covered in progress claim timing. The tool for seeing it coming is a rolling 13-week cash flow forecast that plots each claim, its likely payment date and every outgoing on one page.
Frequently asked questions
What is a progress claim in construction?
A formal request for payment for work completed to date under a building contract, usually made at set stages or on a monthly cycle, and governed by the contract and security of payment legislation.
Is a progress claim the same as a tax invoice?
No, though one document can serve as both. A progress claim triggers the contract's payment process. A tax invoice supports GST. Make sure the document meets both sets of requirements.
How often can I submit a progress claim?
As often as your contract allows, commonly monthly. Under security of payment laws there is generally a limit on how many claims you can make for each reference date. Check your contract and state legislation.
What happens if the principal doesn't pay a progress claim?
Your rights depend on the contract and on whether the claim was valid under the relevant security of payment Act. Get legal advice early, because the response windows are short.
Can a CFO help with progress claims?
A CFO doesn't write your claims, but they build the forecast, WIP schedule and claim calendar that tell you when to claim, how much, and when the cash will land.
Want to see what faster claiming is worth to your business?
Try the value calculator for a conservative two-minute estimate, or book a free strategy session and bring your live job list. We'll tell you plainly where your cash is getting stuck.
General information only, not legal, financial or tax advice. Security of payment rules differ by state; check your contract and get legal advice for your situation.