Job costing vs your P&L: why a builder's profit figure misleads mid-year

Writer: victorzhou
victorzhou
17 hours ago
5 min read

Your P&L tells you what the whole business invoiced and spent in a period. Job costing tells you what each job has earned and what it will earn by the time it finishes. Mid-year, the two often disagree, and when they do, job costing is usually the one telling the truth. A builder who manages on the P&L alone finds out about a losing job at the final account, when nothing can be done about it.

What is the difference between job costing and accounting profit?

Accounting profit is revenue invoiced less costs recorded, across the whole business, for a period. Job costing tracks revenue, costs to date and cost to complete for each individual job, against the budget you tendered. One answers "did the business make money this quarter?" The other answers "which jobs are making it, and which are quietly losing it?"

Both come from the same transactions. The difference is how they are sliced, and whether anyone has looked forward to the end of the job.

Why does a builder's P&L mislead part-way through the year?

There are four common reasons, and most building businesses have at least two of them at once.

1. Claims run ahead of the work. If you have claimed 60% of a contract but done 45% of the work, the P&L shows revenue you have not yet earned. The month looks great. The cost to earn that revenue lands later.

2. Costs arrive late. Subcontractor invoices, supplier statements and variations in dispute often land weeks after the work is done. Until they are entered, the job looks more profitable than it is.

3. One good job hides one bad job. A P&L adds everything together. A job running at 22% and a job running at 2% show up as a healthy business at 12%. The 2% job keeps running exactly as it is.

4. Overheads are not in the job. Your gross margin per job has to cover supervision, vehicles, insurance, the office and you. A job can look profitable at the gross line and still not carry its share.

What does that look like with real numbers?

Here is a simplified, illustrative example. A builder has three live jobs at 31 December.

Job A: contract $2.4M, tendered at 16%. Claimed to date $1.5M, costs to date $1.2M. On the P&L, that is $300,000 of margin, or 20%. It looks ahead of tender.

Job B: contract $1.8M, tendered at 15%. Claimed $900,000, costs $790,000. On the P&L, 12%.

Job C: contract $1.1M, tendered at 18%. Claimed $400,000, costs $330,000. On the P&L, 17.5%.

Add them up and the P&L shows $2.8M of revenue and $480,000 of gross margin, about 17%. A good half.

Now the site leads re-estimate the cost to complete. Job A has been claimed ahead of the work, and the remaining work will cost $960,000, not the $816,000 left in the budget. Its forecast final margin is $240,000, or 10%, not 16%. Job B has an unpriced variation and a subcontractor rate rise, and forecasts at 9%. Job C is on track.

The forecast margin across the three jobs is now roughly $600,000 on $5.3M, a little over 11%, against about 16% tendered. That is around $250,000 of margin gone, and the half-year P&L showed none of it.

Nothing in that P&L was wrong. It was simply answering a different question.

How do you reconcile job costing to your P&L each month?

This is the discipline that makes both reports trustworthy. It takes less time than most builders expect once it is set up.

1. Close the month properly. All supplier and subcontractor invoices entered, including the ones still sitting in someone's ute.

2. Update cost to complete on every live job. The site lead or project manager re-estimates what is left to spend, not the bookkeeper.

3. Calculate forecast final margin per job. Contract value plus approved variations, less costs to date, less cost to complete.

4. Work out the WIP position. For each job, compare what you have claimed against what you have earned based on progress. Over-claimed means revenue to push back out of the P&L. Under-claimed means revenue you have earned but not billed.

5. Adjust the P&L for WIP. After this adjustment, the P&L margin and the job-cost margin should agree. If they don't, something is miscoded, and it is worth finding.

6. Compare forecast margin to tender margin. Any job that has moved more than two or three points gets a conversation that month, not at completion.

We cover the WIP step in more detail in What is WIP in construction accounting, and why does it decide your year?, and where margin goes between tender and final account in Profit fade in construction.

A quick checklist: can you trust your current profit figure?

• Every cost is coded to a job, not to a general "materials" or "subcontractors" account.

• Each live job has a cost-to-complete figure updated in the last 30 days.

• You can name your worst-forecasting job without opening a spreadsheet.

• Your P&L is adjusted for over and under-claims each month.

• Variations are recorded when the work is instructed, not when they are finally approved.

Three or more ticks and your numbers are probably telling you the truth. Fewer than that and your mid-year profit is a guess with decimal places.

Do you need new software to do this?

Usually not. Xero and MYOB both support job or project tracking, and most estimating and project tools used by Australian builders export costs by job. The gap is rarely the software. It is that nobody owns the monthly cost-to-complete update and the reconciliation back to the P&L. That is a process and a person, not a system.

What is it worth to get this right?

On a $10M building business, catching two points of margin fade early is $200,000 a year. The value calculator gives a conservative two-minute estimate for a business your size, using your own turnover and margin.

Frequently asked questions

Is job costing the same as WIP?

No. Job costing tracks costs and revenue by job. WIP is the adjustment that compares what you have claimed with what you have earned on each job. You need job costing to produce a WIP schedule.

Which is right, my P&L or my job cost report?

Both, once the P&L has been adjusted for WIP. If they still disagree after that, costs are miscoded or a job's cost to complete is out of date.

How often should a builder update job costs?

Monthly at a minimum, with cost to complete re-estimated on every live job. Weekly cost entry makes the monthly review much faster.

Why did my accountant not pick this up?

Year-end accounts and tax work look backwards at the whole business. Forecasting each job's final margin is management reporting, and it usually sits outside a compliance engagement unless you have asked for it.

At what size does job costing become essential?

As soon as you have more than two or three live jobs, or any single job large enough that a five-point margin slip would hurt. For most builders that is somewhere past $2M in turnover.

Book a free strategy session

Bring your live job list and last month's P&L. In 30 minutes we will show you where the two disagree and which job deserves your attention first, and tell you plainly if your numbers are already in good shape. Book a time or call 1300 886 347. You can also read more about how a fractional CFO for builders works.

General information only, not financial, tax or legal advice. The worked example is illustrative and does not describe a client.

 
 
 