What profit margin should an Australian builder make? Markup, margin and the number that actually matters
There is no single right profit margin for a builder. The margin you need is the one that covers your overheads and still leaves the net profit you want, and that is different for every business. Work it out in three steps: know your overheads as a percentage of revenue, add your target net profit, then convert that gross margin into the markup you put on cost. Most pricing mistakes happen at the last step.
What is the difference between markup and margin?
Markup is profit as a percentage of cost. Margin is profit as a percentage of the selling price. They describe the same dollars from two different ends, and they are never the same number. A 20% markup on cost gives you a 16.7% margin on price, not 20%.
The conversion is simple:
• Margin = markup ÷ (1 + markup)
• Markup = margin ÷ (1 − margin)
And the common pairs are worth knowing by heart:
• 10% markup = 9.1% margin
• 15% markup = 13.0% margin
• 20% markup = 16.7% margin
• 25% markup = 20.0% margin
• 30% markup = 23.1% margin
What does confusing the two actually cost?
Take a job with $800,000 of direct cost. You want a 20% margin, so you add 20% and quote $960,000. Your profit is $160,000, which is 16.7% of the price. To really earn 20% you needed to quote $1,000,000.
That is $40,000 left out of one job, before a single thing has gone wrong on site. Price five jobs that size the same way in a year and you have given away $200,000 without ever knowing it. Nobody on site caused it and no report will show it, because the job came in exactly on budget.
How do you work out the margin your business needs?
Start with overheads, not with what the market seems to be charging.
1. Add up your annual overheads. Everything that is not a direct job cost: office, vehicles not charged to jobs, insurance, software, admin and estimating wages, and a proper salary for you.
2. Divide by revenue. That percentage is your break-even gross margin. Below it, every job you win loses money for the business even if the job itself looks fine.
3. Add your target net profit. The result is the gross margin you need to tender at, on average, across the year.
4. Convert it to markup. Use the formula above, and put that number in your estimating template so nobody is doing it in their head.
Here is an illustrative example. A builder turns over $6M with $780,000 of overheads. That is 13% of revenue, so 13% gross margin is break-even. The owner wants 5% net profit, so the business needs 18% gross margin. Converted, that is a markup of about 22% on cost. A flat "20% on everything" would deliver 16.7% gross and 3.7% net, on a good year.
Why does a small margin slip hurt so much?
Because net profit is what is left after overheads, and overheads do not shrink when a job goes badly.
Stay with the same builder, but say they tender at 15% gross. After 13% of overheads there is 2% left: $120,000 on $6M. Now one $2M job fades by three points. That is $60,000, which is half the year's profit, from one job slipping a little.
This is why the gap between gross margin and your overhead percentage matters more than the gross margin itself. A business at 18% gross with 13% overheads has room for a bad job. A business at 15% does not. We cover where margin goes between tender and final account in Profit fade in construction.
What should be counted as a job cost and what is an overhead?
There is more than one sensible answer, but you have to pick one and stick to it. Site supervision, site vehicles, project management time and equipment used on a job are usually better treated as job costs, because they rise and fall with the work. Head office, estimating, admin and the owner's salary are usually overheads.
What matters is consistency. If supervision sits in overheads when you estimate and in job costs when you report, your tender margin and your achieved margin can never be compared. Our post on job costing vs your P&L walks through how to reconcile the two each month.
A quick checklist: is your margin doing its job?
• You know your overheads as a percentage of revenue, to the nearest point.
• Your estimating template uses markup that has been converted from a target margin, not a round number.
• You compare tender margin with forecast final margin on every live job each month.
• You know which type of work earns your best margin, and which earns your worst.
• Variations are priced with the same margin as the original contract, not at cost plus a token amount.
Fewer than three ticks and your margin is probably lower than you think it is.
How can a builder lift margin without simply charging more?
Raising price is one lever, and often the hardest one in a competitive tender. Four others usually move first:
• Price and claim every variation. Unclaimed variations are margin given away after the job is won.
• Re-estimate cost to complete monthly. A job caught at two points of fade can be recovered. One caught at the final account cannot.
• Choose your work. If one type of job consistently earns five points less, tendering for fewer of them lifts the average without touching a price.
• Watch overhead creep. Overheads that grow faster than revenue raise your break-even point quietly, a point at a time.
The value calculator gives a conservative two-minute estimate of what a few points of margin are worth for a business your size. The 5 numbers every builder should check monthly covers the short list worth tracking.
Frequently asked questions
What is a good profit margin for a builder in Australia?
One that covers your overheads and leaves the net profit you need. Work out overheads as a percentage of revenue, add your target net profit, and that is the gross margin to tender at. A figure borrowed from another builder tells you nothing about your own break-even.
Is markup the same as margin?
No. Markup is profit as a percentage of cost, margin is profit as a percentage of price. A 20% markup is a 16.7% margin, and a 25% markup is a 20% margin.
How do I calculate my break-even margin?
Divide your annual overheads by your annual revenue. If overheads are $780,000 on $6M of revenue, break-even gross margin is 13%. Every point of gross margin above that is net profit.
Should overheads be included in job costs?
Head office overheads usually sit outside job costs and are recovered through gross margin. Costs that move with the work, such as site supervision, are usually better inside the job. Whichever way you choose, estimate and report the same way.
Why is my achieved margin lower than my tender margin?
The usual causes are unclaimed variations, costs that were not in the estimate, cost to complete that was never updated, and markup applied as if it were margin. Comparing forecast final margin with tender margin on each job every month shows which one it is.
Book a free strategy session
Bring your last twelve months of overheads and your current job list. In 30 minutes we will work out your break-even margin, check it against what you are tendering at, and tell you plainly if your pricing is already sound. Book a time or call 1300 886 347. You can also read more about project profitability and WIP for builders.
General information only, not financial, tax or legal advice. The worked examples are illustrative and do not describe a client.