Profit fade in construction: why an 18% tender becomes a 6% job
Updated: 2 days ago
Profit fade is the gap between the margin you priced at tender and the margin the job actually finishes on. A builder who tenders at 18% and lands at 6% hasn't had one bad month. They've lost a point here and two points there, across variations, labour, subcontract packages and time, with nobody looking at the forecast margin until the final account. The fix is not tighter tendering. It is re-forecasting every live job's cost to complete every month, and acting while there is still time to recover.
What is profit fade in construction?
Profit fade is margin leaking out of a job between the day you win it and the day you close the final account. It is rarely one big blow-up. It is a dozen small ones that never show on a business-wide P&L because the profits from other jobs cover them up.
If your tender allowed 18% and you finish on 6%, that is twelve points of margin gone. On a $2.4M job that is roughly $288,000 of profit that was in the price and never reached the bank. Fade of 5 to 12 points between tender and final account is common on Australian commercial work, and most of it is avoidable if it is caught early.
Where does the margin actually go?
1. Variations that are never priced, approved or claimed. The client asks, the site team says yes, the paperwork follows "when things calm down". They don't, and the cost lands on the job with no matching revenue.
2. Labour overruns nobody tracks weekly. Hours are over budget by week three, but the timesheets only get looked at when the job is finished.
3. Subcontract packages let above allowance. The tender assumed one price, the package came in higher, and the difference quietly came out of your margin on day one.
4. Cost to complete that is never re-forecast. Budgets get set at tender and left alone. "On budget" really means "we haven't checked."
5. Preliminaries running past the program. Every extra week of site sheds, supervision, scaffold hire and insurance is paid for out of margin unless an extension of time is claimed.
How early can you detect profit fade?
Usually by about week four, if you are looking at the right number. Costs to date will not tell you. A job can have spent 30% of budget and still look fine. What tells you is forecast margin: revenue at completion minus forecast cost at completion, re-estimated monthly by the person who knows the job. If a job's forecast margin falls two months in a row, treat it as a warning, not a rounding error, and go back to the five places above to find which one moved.
What is the difference between job costing and your P&L?
Your P&L tells you how the whole business performed over a period. Job costing tells you how each project is performing against what you priced. A healthy P&L can sit on top of a loss-making job, because five good jobs hide one bad one. By the time the P&L shows the damage, that job is usually finished and the money is gone. Job costing is forward-looking and per project, the only report that lets you change the outcome of a job you're still building. For more on how this connects to cash, see our post on why profitable builders run out of cash.
What should you check on every live job each month?
• Original tender margin, current forecast margin, and the movement between them.
• Approved variations versus unapproved ones, and what has actually been claimed.
• Labour hours spent versus budget, by trade or cost code.
• Subcontract commitments versus allowances, including packages not yet let.
• Estimated cost to complete, signed off by the project manager, not carried forward from last month.
• Programme status and any extension of time claims lodged.
• Over- or under-claimed position from your WIP schedule.
If you can't produce most of this for every job within a day of month-end, you're running on hope.
What do you do when you spot fade?
Early is the whole game. In week four you can still price the variation, renegotiate the next package, reallocate labour or claim the extension of time. In week thirty you can only explain it to your accountant. The point of the monthly review isn't to produce a report. It is to give the person running the job one clear decision to make while it still matters. If you want a rough sense of what recovered margin could be worth, the value calculator gives a conservative two-minute estimate.
Fade is measured against the margin you tendered at, so it pays to know that number is right in the first place. See what profit margin should an Australian builder make for how markup and margin differ and how to work out the margin your overheads require.
Frequently asked questions
What is profit fade in construction?
The drop between the margin you tendered and the margin the job finishes on, caused by unpriced variations, labour and subcontract overruns, stale cost-to-complete figures and extended preliminaries.
How much profit fade is normal?
It varies by project type and contract, but fade of 5 to 12 margin points is common on Australian commercial work. The aim isn't zero, it's seeing it early.
How do I measure forecast margin?
Take contract value plus approved variations, subtract your latest estimate of total cost at completion, and divide by revenue. Re-do it every month.
Is job costing the same as WIP reporting?
No. Job costing tracks cost and margin per project. WIP reporting compares what you have earned and claimed to what you have spent, so it shows over- and under-claiming. You need both.
When should a builder get help with job costing?
When jobs regularly finish below tender margin, when you can't say which live job is forecasting worst without digging, or when the owner is the only person who knows the real numbers.
See your margin before it fades
Our project profitability service builds the monthly job report and keeps it current. Or book a free strategy session, bring your live job list, and we'll walk through where your margin is heading, and tell you plainly if you're fine as you are. Call 1300 886 347 if you'd rather talk.
General information only, not financial, tax or legal advice.
Comments