Construction cash flow forecasting: how to build a 13-week forecast that actually works
A 13-week cash flow forecast is a rolling, week-by-week projection of every dollar you expect to receive and pay over the next quarter. For a builder it is built around job timing, not accounting periods: when each progress claim will really be paid, when retentions release, and when wages, subbies, super, BAS and PAYG fall due. It is the one report that tells you, six weeks out, whether payroll clears.
Your P&L tells you whether you made money. Your bank balance tells you where you were. Neither tells you where you are heading, which is why profitable builders still run short.
Why do builders need a 13-week forecast instead of a normal cash flow statement?
A standard cash flow statement is a look back. It shows last month or last year, usually weeks after the event. By then the shortfall has already happened.
A builder's cash moves in lumps that don't line up with months: a big claim lands late, a retention sits for a year, a supplier account falls due the same week as BAS. A weekly view over thirteen weeks (one quarter) is long enough to catch a full BAS cycle and most progress-claim cycles, and short enough that the numbers are still knowable rather than guesses. Beyond thirteen weeks you are forecasting. Inside it you are planning.
What goes into a construction cash flow forecast?
Cash in
• Progress claims, by job, at the date you expect them to be paid, not the due date on the invoice.
• Retention releases, by job, at the date they are realistically released.
• Approved variations that have been claimed.
• Other receipts: deposits on new contracts, GST refunds, asset sales.
Cash out
• Wages, super and PAYG withholding, on their actual due dates.
• Subcontractors and suppliers, by the terms you actually pay on.
• Plant hire, vehicle and equipment finance, insurance premiums.
• BAS and GST, instalments and tax.
• Overheads: rent, software, accountants, and your own drawings.
• Retention you hold back from your subcontractors, and when it is due to them.
Everything sits in weekly columns. The bottom line is your opening cash, movements and closing cash for each week, plus the one number that matters most: the lowest point in the thirteen weeks and which week it hits.
How do you build a 13-week cash flow forecast, step by step?
1. Start with the bank. Put in this week's opening balance, and your overdraft or facility limit as a separate line so you can see headroom.
2. List every live job and its next three claims. Use your WIP schedule and contract claim dates.
3. Replace contract terms with real payment behaviour. If a client's terms are 30 days but they have paid in 50 on the last five claims, the forecast says 50.
4. Add retentions. Leave them out and the forecast looks healthier than the business is.
5. Load the fixed outgoings first (wages, super, rent, finance), then subbies and suppliers by their real payment dates.
6. Layer in the lumpy items: BAS, PAYG instalments, insurance renewals, annual registrations.
7. Find the low point. Highlight the week your closing balance is lowest and compare it with your facility limit.
8. Roll it weekly. Drop the week just finished, add a new week 13, and replace forecasts with actuals.
What does a cash gap look like in practice?
Here is an illustrative example, not a client figure. A builder turning over about $6M has three live jobs. Wages, super and rent run roughly $55,000 a week. A $240,000 claim on the largest job is due on paper in week 4, but that client has historically paid in around 50 days, so the forecast lands it in week 8. BAS of $60,000 falls in week 6.
On the bank balance, everything looks fine in week 1. On the forecast, the business is roughly $190,000 short by week 6 and stays there until the claim lands in week 8. With six weeks' notice, that builder can bring forward a claim, renegotiate a supplier date, or arrange facility headroom. With one week's notice, the only option is a stressed phone call to the bank.
What are the most common cash flow forecasting mistakes in construction?
1. Using invoice due dates instead of realistic payment dates. The single biggest source of forecasts that look fine and are not.
2. Leaving retentions out. Typically 5 to 10 per cent of contract value, and they can sit for a year or more.
3. Updating monthly. A monthly forecast is a document. A weekly one is a decision tool.
4. Mixing up profit and cash. A job can be on budget and still drain cash if you pay out faster than the client pays in. Our post on why profitable builders run out of cash walks through this.
5. Forgetting the tax lumps. BAS, PAYG instalments and super do not arrive as a surprise to the ATO, only to the builder who didn't plan for them.
How do you improve the forecast once you have it?
The forecast is only useful if it changes what you do. Once you can see the low point, the levers are specific: tighten claim timing (see our progress claim timing guide and the explainer on what a progress claim is), chase retentions on a diary, stage supplier payments, or arrange facility headroom before you need it. If you want a rough idea of what better cash visibility could be worth to your business, the value calculator gives a conservative two-minute estimate. For a simple monthly check, start with the 5 numbers every builder should check monthly.
Frequently asked questions
What is a 13-week cash flow forecast?
A rolling, week-by-week projection of cash in and out of the business over the next quarter, built on project timing: progress claims, retention releases, subcontractor and supplier payments, wages, super, BAS and tax.
Why 13 weeks and not 12 months?
Thirteen weeks is one quarter, long enough to capture a BAS cycle and most progress-claim cycles, short enough that the inputs are still knowable. A 12-month forecast is useful for strategy, but too coarse to tell you whether next month's payroll clears.
How often should a builder update the forecast?
Weekly. Each week drops off the front and a new week 13 is added at the back, with actuals replacing forecasts. Updated weekly, you see a shortfall six weeks out while you still have options.
Can I build a construction cash flow forecast in Excel or Xero?
Yes. Many builders start with a spreadsheet fed from their accounting software and job schedule. The hard part is not the tool; it is the discipline of using realistic payment dates and updating it every week.
When should a builder get help with cash flow forecasting?
When the business is profitable on paper but regularly short of cash before claims land, when you run more than two or three live jobs, or when a bank or surety asks for forward-looking numbers you can't produce quickly. A part-time CFO can build and maintain the forecast alongside your bookkeeper and accountant.
See a cash crunch before it arrives
Our cash flow forecasting service builds the 13-week forecast and keeps it current. Or book a free strategy session and bring your live job list and last three months of reports. We'll walk through your cash position live, and tell you plainly if you're fine as you are. You can also call 1300 886 347.
General information only, not financial, tax or legal advice.
Comments